Contract 56662 REL 72: 1996-040-00 CAP MID-C COHO HATCHERY CONSTRUCTION
Project Number:
Title:
Upper Columbia Production
BPA PM:
Stage:
Implementation
Area:
Province Subbasin %
Columbia Cascade Methow 40.00%
Wenatchee 60.00%
Contract Number:
56662 REL 72
Contract Title:
1996-040-00 CAP MID-C COHO HATCHERY CONSTRUCTION
Contract Continuation:
Previous: Next:
56662 REL 21: 1996-040-00 CAP MID-COLUMBIA (COHO) REINTRODUCTION
Contract Status:
Closed
Contract Description:
As part of the long term coho reintroduction plan, several sites will need to be constructed and/or rehabilitated for acclimation during the next 3 years.  Focus locations in 2015 will center around modifications to the Beaver Creek inlet to provide access for listed species to the site while continuing to maintain site integrity as well as Natapoc access road work to include installation of utilities and road improvements to the site.  A land acquisition may be considered for the current location of the Nason Creek smolt trap as the landowner who currently YN has a landowner agreement with has expressed the need to sell the property and given its importance to continued operations at this location, it would be considered a project priority for monitoring Nason Creek coho population estimates.  Most of the projects construction will begin in 2016 and continue into 2017 as needed.
Account Type(s):
Capital
Contract Start Date:
02/01/2015
Contract End Date:
01/31/2016
Current Contract Value:
$56,990
Expenditures:
$56,990

* Expenditures data includes accruals and are based on data through 31-Oct-2024.

BPA CO:
Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Cost Reimbursement (CNF)
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Debbie Azure Yakama Confederated Tribes Yes Administrative Contact azud@yakamafish-nsn.gov (509) 865-5121x6334
Roy Beaty Bonneville Power Administration Yes COR rebeaty@bpa.gov (503) 230-5213
Michelle Guay Bonneville Power Administration Yes Env. Compliance Lead mxguay@bpa.gov (503) 230-3459
Tana Hoptowit Yakama Confederated Tribes Yes Administrative Contact hopt@yakamafish-nsn.gov (509) 865-5121x6318
Cory Kamphaus Yakama Confederated Tribes Yes Contract Manager kamc@yakamafish-nsn.gov (509) 548-9413x102
Peter Lofy Bonneville Power Administration Yes F&W Approver ptlofy@bpa.gov (503) 230-4193
Khanida Mote Bonneville Power Administration Yes Contracting Officer kpmote@bpa.gov (503) 230-4599
Keely Murdoch Yakama Confederated Tribes Yes Technical Contact murk@yakamafish-nsn.gov (509) 548-2206
Thomas Scribner Yakama Confederated Tribes Yes Supervisor scrt@yakamafish-nsn.gov (503) 331-9850
Gregory Wolfe Yakama Confederated Tribes No Interested Party wolg@yakamafish-nsn.gov (509) 881-0674


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
All the appropriate coverage needed for construction work at Beaver Creek Pond and Natapoc access B: 165. NEPA, SEPA, and ESA review and approval 01/31/2016 01/31/2016
All administrative tasks fulfilled with timely quality products C: 119. Monitor Beaver Creek project in the Wenatchee basin 11/30/2015 11/30/2015
Construct/develop/install upgraded surface water intake at Beaver site for coho releases D: 171. Beaver Cr. Pond (WEN) -intake removal/roughen channel installation 11/01/2015 11/01/2015
subcontract for native plantings-revegetation F: 47. subcontract revegetation plantings for the site identified in 2015 01/31/2016 01/31/2016

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
Coho (O. kisutch) - Unspecified Population
  • 1 instance of WE 47 Plant Vegetation
  • 1 instance of WE 171 Build, Modify, and/or Refurbish Artificial Production Facility

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 185 Periodic Status Reports for BPA 02/01/2015
B 165 NEPA, SEPA, and ESA review and approval 02/01/2015
C 119 Monitor Beaver Creek project in the Wenatchee basin 02/01/2015
D 171 Beaver Cr. Pond (WEN) -intake removal/roughen channel installation 02/03/2015
E 132 Report waived by COTR 02/01/2015
F 47 subcontract revegetation plantings for the site identified in 2015 02/03/2015